Leighton SBM installation at Bhogat November 2011 to January 2012
January 2012

Cairn (India) saw FC Rija as their best candidate to assistance onsite at Bhogat after a breakdown of the designated crane. FC Rija was mobilized on an urgent basis from Mumbai by Leighton, the contractors, for the final scope of SBM unit installation. Tug Aqua Boat was the towing tug for the duration of the project for FC Rija. FC Rija was working alongside Accommodation barge Eastwind 365.